« »

In the Gutter

May 27, 2013

It was a rather miserable day for island life and I spent more of it shuttling back and forth with 4 boat trips. Jose was up to finish the gutter part of the roofing contract so we are 100% on the roof as of today. We also had Rick from Breeze Air Contracting help out with the building ventilation and bathroom fans (kind of a silly thing considering we have never had a fan but the Building Code requires all bathrooms to have one). In any event, we now have 4 bath fans and a hood fan duct installed. I was concentrating on continuing with the electrical (had to be concentrating as yesterday I severed a gas line with the drill).